Construction
schedule of the Vizhinjam transshipment terminal may go haywire as the Kerala
government has failed to convince the agitating fishermen to give up their
protests against the project. Work on the construction of the terminal has come
to a standstill for the past one week as the fishermen from neighboring
villages have blockaded the area.
According to the Original schedule the
first vessel carrying equipment for works can berth here by March 2023 and the
400-meter berth would be readied by May 2023, if there are no major issues in the course of the work,” said
officials close to the port developer was quoted by local media reports
Adani
group which is constructing the port have stopped all the civil works for they
do not want confrontation with the local
community. The state government is however persuading them to resume work.
All
the issues raised by the protesters were supposed to be addressed by the State
government and not by the port developer according to a port official.
Hardly
fifty per cent of the breakwater construction and capital dredging work in the
port project has been completed so far. Berth construction could start only
after completion of these works said the
official
A spokesman of the Kerala government however maintained that no major construction work takes place in the coast during the south west monsoon period between June and September. Hence the fishermen agitation is not bound to affect the project schedule. The present disruption will not cause any delay in the first phase of commissioning.
The port had earlier decided to allow ships
only after completing an 800-meter-long berthing facility at the port. But now
we have decided to commission the first phase on completion of 400-meter berth
as almost all the big container vessels are 400 meters long, the official was
quoted by local newspapers.
Work
on the port project commenced way back in 2015. An ambitious schedule was set
by the Adanis to complete the first phase of the project in one thousand days.
It should have been completed before 2018. Series of cyclones which hit the
project site had washed away major part of the breakwaters when they were being
constructed. Stones used for building breakwaters were in short supply and they
were being procured from neighboring Tamil Nadu. Now the fishermen backed by
the church are opposed to the project saying their livelihood is affected due
to sea erosion because of the project.
The church backed fishermen sabotaged a
similar project in neighboring Tamil Nadu at Colachel. The project cleared by the Union cabinet way back in
2016 is hanging in balance. The shipping ministry is yet to declare whether the
project is alive or dead.