The much delayed bullet train project from
Ahmedabad to Mumbai is trying to make up for the five year loss of time with the
railway board and Gujarat government working overtime to make progress
The project had since overcome a major hurdle with the
change of regime in Maharashtra last year when BJP became part of the state
government
One of the notable achievements is the
completion of 61.3 kilometers of viaduct, which includes a continuous viaduct
of 12.6 kilometers near Vadodara and the construction of 48.7 kilometers at
various other locations," an official of the National High Speed Rail
Corporation ( NHRCL) was quoted by media reports.
Construction activities are currently in full swing
across the alignment, which
passes through eight districts of Gujarat and Dadra and Nagar Haveli. Work on
the eight high-speed rail stations, spanning from Vapi to Sabarmati, is
progressing at various stages. Notably, the Anand/Nadiad HSR station has
achieved a significant milestone by completing the concourse level, which is
the first level of the station, spanning 425 meters in length. Rail level slab
casting has commenced at Surat, Anand, and Bilimora HSR station," said an
official.
In addition, bridge construction work is
underway over important rivers such as Narmada, Tapti, Mahi, and Sabarmati. The
Par River Bridge has become the first river bridge to be completed,
accomplishing this feat in January 2023.
A dedicated training facility with three trial lines has
been established at the Surat Depot. Approximately 20 Japanese experts are actively
providing intensive training to Indian engineers, supervisors, and technicians,
certifying their skills and knowledge.
Asked about progress of this Project in
Maharashtra , an official said, "Work of construction of underground
station in BKC and tunnel up Shilphata has already started, which will be
completed within 5 year.
Work on the Ahmedabad Mumbai
High-Speed ( 508 km) bullet train
project started way back in 2017 and was scheduled to be completed in 2023.
As per the current schedule Rs Two Lakh
crore project is likely to be completed 2028 if everything goes well. The project is fully funded by an interest
free loan from a Japanese bank.