Identified as Yard 326, DSC
A21 features a catamaran hull and specialised diving equipment. Its delivery
advances a procurement programme intended to support naval vessels operating in
and around harbours, including underwater maintenance and repair work. The craft’s twin-hull configuration
provides stability, additional working deck space and seakeeping
characteristics suited to diving support, according to the Ministry of
Defence. DSC A21 was designed and
built under the relevant naval rules and regulations of the Indian Register of
Shipping (IRS). Hydrodynamic analysis and model testing during the design stage
were undertaken by the Naval Science and Technological Laboratory (NSTL) in
Visakhapatnam. These activities supported the development of the vessel’s hull
and its performance in water. Earlier
programme announcements described the craft as platforms for both operational
and training dives in harbours and coastal waters. Their role includes
providing the equipment and working platform needed for divers undertaking
underwater tasks. The project therefore supports routine fleet maintenance
alongside inspection and salvage requirements. The Ministry of Defence signed the
contract for five diving support craft with Titagarh Wagons Limited,
subsequently renamed Titagarh Rail Systems Limited, on 12 February 2021. The procurement covers Yards 325 to 329 at
a total project cost of ₹174.77 crore. That figure applies to the five-craft
programme rather than DSC A21 alone. A ministry update in August 2022, issued
when the third vessel’s keel was laid, identified underwater repairs,
maintenance and salvage as core requirements for the new fleet. At the launch of the first craft in August
2023, the ministry described the vessels as approximately 30 metres long, with
a displacement of around 300 tonnes. A subsequent programme update in August
2026 placed their displacement in the 300–400-tonne range. The first vessel, DSC A20, was launched
into the Hooghly River at Titagarh, Kolkata, on 31 August 2023. The keel of the
fifth and final craft, DSC A24, was laid during the same event, marking
simultaneous construction across the five-vessel programme. The 2023 announcement had anticipated
delivery of all five craft during financial year 2024–25. DSC A21’s November
2026 handover falls beyond that earlier programme target. The latest delivery
announcement does not explain the change in schedule. DSC A24, designated Yard 329, was launched
on 1 August 2026 at Titagarh. That event marked the launch of the final vessel
in the series, while the latest announcement concerns the delivery of DSC
A21. The programme combines domestic
ship design and construction with Indian classification and naval research
capabilities. In its August 2026 update, the ministry said 70 per cent of the
craft’s main and auxiliary equipment was sourced from Indian manufacturers. That equipment share provides a measure of
domestic supplier participation in the specialised vessel programme.
Alongside Titagarh’s
construction work, the involvement of IRS and NSTL illustrates the contribution
of classification, engineering and testing organisations to delivering naval
support platforms.