The terminal will occupy a 111-acre site
and have a 900-metre-long quay, a berth width of 30 metres and a depth of 20
metres alongside. It is designed to handle container ships up to 400 metres
long with a capacity of up to 24,346 TEUs.
The additional capacity is intended to serve containerised export and
import cargo from the Chennai–Ennore industrial region and the wider southern
hinterland. The government expects the deeper terminal to support more direct
calls by large mainline vessels. For shippers, direct services could reduce
reliance on feeder connections through overseas transhipment hubs and lower the
associated costs. Kamarajar Port
handled 49.08 million tonnes of cargo and received 1,008 vessels in the 2025–26
financial year, including container throughput of about 700,000 TEUs. The
government reported that the port’s overall cargo volume grew at a compound
annual rate of 13.64 per cent over the preceding five years. The government proposes to select the
private concessionaire through open global bidding. Under the design, build,
finance, operate and transfer (DBFOT) model, the winning bidder will arrange
financing, build and operate the terminal, and recover its investment through
user charges governed by the concession agreement and applicable tariffs. The
planned concession runs for 40 years.
The estimated private investment comprises ₹2,429.32 crore for the first
phase and ₹1,858.94 crore for the second. Kamarajar Port Limited is expected to
spend a further ₹450 crore on dredging. The project proposal calls for
environmental and other necessary clearances to be obtained before the bid
deadline.
The first phase, with annual capacity of
1.1 million TEUs, is scheduled for completion within 24 months of the
concession award. Commercial operations are due to start in month 25.
Construction of the second phase, which adds capacity of 900,000 TEUs a year,
is scheduled to run from month 25 through month 48. Full commercial operations
are due to begin in month 49.