The change was notified
on September 22, 2026, through an amendment to the Environment Impact
Assessment (EIA) Notification, 2006. The move follows recommendations from
expert appraisal committees that the earlier validity period was insufficient
for projects with long gestation periods and phased development. Under the amended framework, environmental
clearances for eligible port and harbour projects will initially remain valid
for 20 years. Projects can subsequently seek an extension of up to five years,
subject to an assessment of existing environmental safeguards. A further extension of up to five years may
be considered in deserving cases where a project has still not become
operational after the first extension. The Expert Appraisal Committee or
State-level Expert Appraisal Committee may also recommend additional
environmental safeguards for inclusion in the project’s Environmental
Management Plan. Previously,
environmental clearances for ports and harbours were valid for 10 years, with
only a one-year extension available. The revised framework is intended to
address the lengthy development timelines associated with major maritime
infrastructure, including projects built in multiple phases. The longer validity period could provide
greater regulatory certainty for developers undertaking port construction,
expansion, modernisation, breakwater development and dredging activities. It
may also reduce the need for projects facing delays to restart the
environmental clearance process after the previous validity period expires. The government has linked the change to the
long gestation and phased development characteristics of port and harbour
projects. The Ministry of Ports, Shipping and Waterways had also sought a
longer validity period during consultations on the proposed amendment. The revised rules are expected to support
the development of long-term maritime infrastructure while retaining provisions
for environmental safeguards through periodic reviews when extensions are
sought.