The bidders include
DP World Ltd, which has applied
through its Indian arm Hindustan Ports
Pvt Ltd; NMDC Dredging &
Marine, understood to be supported by Dutch dredging major Royal Boskalis B.V.; Adani Ports and Special Economic Zone Ltd
(APSEZ), which has partnered with Van Oord, Jan De Nul and ISDPL (DEME Group); and Hyderabad-based Vishwa Samudra Holdings Pvt Ltd. The
tender closed on September 23. The
contract covers dredging, reclamation and construction of an offshore protection
bund over 1,207 hectares of reclaimed
land, to be developed in two phases. The project is the largest of the
three major components of the Vadhvan Port development. The ₹76,220-crore
Vadhvan Port is being implemented by Vadhvan Port Project Ltd (VPPL), a joint venture between the Jawaharlal Nehru Port Authority (JNPA),
which holds a 74% stake, and the Maharashtra
Maritime Board (MMB), with the remaining 26%. The proposed port is
designed to handle 298 million tonnes
of cargo annually, including 23.2
million TEUs. The Vadhvan
project comprises three key construction packages. The first is the near-shore reclamation and associated
infrastructure, required to provide a landing facility for offshore port
development. The ₹1,648-crore package was awarded in December 2024 to Cemindia Projects Ltd, formerly ITD
Cementation India Ltd. The second
component is the 10.14-km-long
breakwater, described as the longest breakwater planned for an Indian
port. The ₹5,301.25-crore contract has been awarded to Afcons Infrastructure Ltd.
The third and largest component is the ₹22,323.47-crore HAM package
covering dredging, offshore reclamation and construction of the protective
bund. Under the approved HAM structure,
45% of the project cost will be paid by
VPPL, while the remaining 55%
will be financed by the private PPP operator through a variable annuity
mechanism. The concession period is 15 years, comprising five years of construction—in two
phases of three and two years—and 10
years of operation and maintenance. The 45% public contribution will be
released in five equal instalments during construction, while the balance will
be paid through variable annuity payments, including interest on residual debt,
based on the value of assets created.
The estimated O&M cost for the shore protection bund over 10 years
is ₹171.79 crore. The contract
will be awarded to the bidder quoting the lowest cost. The HAM package represents the first PPP-HAM implementation in India
involving dredging, offshore reclamation and shore protection works for a new
port, making the Vadhvan project significant for the country’s port
infrastructure sector. Once completed,
Vadhvan Port is planned to have nine
container terminals with a combined quay length of 9,000 metres,
supported by more than 100 quay-side
gantry cranes capable of handling vessels of 350 metres or more in
length. The port will also include liquid cargo berths, a Ro-Ro facility,
general, coastal and breakbulk cargo berths, a common rail yard, tank farms and
storage facilities. The container terminals are expected to be developed
separately on a PPP basis after completion of the core port
infrastructure. The Vadhvan Port is
targeted for commissioning by 2030
and is positioned as a major addition to India’s western maritime gateway
infrastructure.